Bioreactor -Temperature update
November 19th, 2008
Not quite sure what's happening? The initial test pile kept rising steadily in temperature, the next morning it was at 76.5f.
Bioreactor - Fill her up!
November 16th, 2008
We've started filling the reactor over the past few days, mainly with leaves and grass cuttings.
Bioreactor - The days after the big day!
November 13th, 2008
So things didn't quite go to plan on Sunday, but over the last few days we finished the reactor in between unexpected bursts of rain.
Bioreactor - The Big Day!
November 10th, 2008
Yesterday was construction stage 2 - the fitting of the reactor. Almost went to plan, but not quite ![]()
Bioreactor - Completion of Construction Stage 1
November 6th, 2008
All the panels are now finished and filled with insulation. The roof panels have been covered in plastic sheet, and have a wooden frame fitted around the edges for protection. The tubes that will hold the pipework in place, as well as ventilating the reactor, have all been drilled ready for installation.